| Project | ISO 5 Cleanroom — Hazardous Exhaust & Process Cooling Renovation |
|---|---|
| Location | Golden, Colorado |
| Owner | National Renewable Energy Laboratory (NREL) |
| Delivery | Mechanical renovation · ASE construction with in-house field engineering, inside an operating ISO 5 cleanroom |
| Completed | September 2025 |
| Systems | Hazardous exhaust for LPCVD tool installation · welded 316 stainless steel ductwork · existing-conditions Revit modeling · off-site prefabrication |
NREL needed a hazardous exhaust system added to support an LPCVD tool installation — inside an ISO 5 cleanroom that had to keep operating. At that classification there is no room for improvisation: every penetration, every weld, and every hour of downtime has to be planned before anyone touches the space.
ASE moved the risk out of the cleanroom and into the model and the shop. Detailed existing-conditions Revit models were produced first, so routing and tie-ins were resolved on a screen. Welded 316 stainless ductwork was prefabricated off-site. All in-room work was then sequenced through formal Method of Procedure activities coordinated with the lab — and those MOPs were written with the crew that would weld the duct, not handed to them, because the people who will be in the room know best where the risk actually sits.
An operating ISO 5 cleanroom at a federal laboratory. The room had to remain classified and functional throughout; access was limited to scheduled MOP windows.
The system was installed with downtime limited to the scheduled MOP windows — the cleanroom remained fully functional throughout construction. The project demonstrates the combination that defines ASE's critical-environment work: accurate modeling, prefabrication, disciplined field sequencing, and respect for an operating facility.